2010年8月,在昌原的Hyosung工厂,机舱的工厂测试以及IO测试成功完成。仅仅在3周之后,Hyosung就在Jeju岛上完成了新2MW样机的安装以及主线缆的最后安装。
调试以及并网
Kk人员亲自前往风场参与调试工作。第一阶段首先确认所有的安全设备以及控制系统都工作正常。最后一周,即调试完成仅2周之后,就完成风机与电网并网发电。
里程碑
在如此短的时间内就能并网发电确实是不小的成就。Kk以及Hyo-sung在此项目上的专注,过硬的技术,良好的合作以及很好的适应能力是此项目成功的关键。双方都对此成就感到骄傲。在接下来的时间,风机会全功率运行,风机的认证准备工作也将开始。
调试以及并网
Kk人员亲自前往风场参与调试工作。第一阶段首先确认所有的安全设备以及控制系统都工作正常。最后一周,即调试完成仅2周之后,就完成风机与电网并网发电。
里程碑
在如此短的时间内就能并网发电确实是不小的成就。Kk以及Hyo-sung在此项目上的专注,过硬的技术,良好的合作以及很好的适应能力是此项目成功的关键。双方都对此成就感到骄傲。在接下来的时间,风机会全功率运行,风机的认证准备工作也将开始。
The Hyosung - 2 MW project successfully up and running within scheduled time
August 2010 the Factory Acceptance Test, FAT (I/O test) of the nacelle was completed with success at Hyo-sung’s factory in Changwon. Only 3 weeks later Hyosung was able to finish the erection of the new 2MW protoype turbine on Jeju Island, as well as final installation of the main cables.
Commissioning and on grid
kk-electronic went on-site to participate in the commissioning of the turbine. The first period of time was spent on confirming that all safety and control systems were working correctly. Last week, after only two weeks of commissioning, the turbine was connected to the grid and producing power.
Reaching the milestone
Reaching the milestone of producing power to the grid within this short period of time is quite an achievement. Focus, proper craftsmanship, good cooperation and flexibility from both Hyo-sung and kk made this achievement possible. Both Hyosung and kk can be very proud of this achievement. In the coming days the power production will be increased to full capacity and preparations for certification of the turbine will begin.
August 2010 the Factory Acceptance Test, FAT (I/O test) of the nacelle was completed with success at Hyo-sung’s factory in Changwon. Only 3 weeks later Hyosung was able to finish the erection of the new 2MW protoype turbine on Jeju Island, as well as final installation of the main cables.
Commissioning and on grid
kk-electronic went on-site to participate in the commissioning of the turbine. The first period of time was spent on confirming that all safety and control systems were working correctly. Last week, after only two weeks of commissioning, the turbine was connected to the grid and producing power.
Reaching the milestone
Reaching the milestone of producing power to the grid within this short period of time is quite an achievement. Focus, proper craftsmanship, good cooperation and flexibility from both Hyo-sung and kk made this achievement possible. Both Hyosung and kk can be very proud of this achievement. In the coming days the power production will be increased to full capacity and preparations for certification of the turbine will begin.
Hyosung 集团副总裁Dong-Soon(Dan) Kim先生表示:“我们对kk电子为按时完成测试以及调试工作所投入的热情及努力非常满意”。
“We are very satisfied with the effort and enthusiasm shown by kk-electronic in order to complete the tests and commissioning in time” Mr. Dong-Soon(Dan) Kim, Vice President Hyosung Corporation